High-rise site: what if service elevator is down on pump day?
We have 40 guys on a high-rise job in Phoenix, 18 floors up. The GC put two standard units and one ADA-compliant unit in a service elevator lobby.…
46 questions across all categories.
We have 40 guys on a high-rise job in Phoenix, 18 floors up. The GC put two standard units and one ADA-compliant unit in a service elevator lobby.…
OSHA 1926.51(c) requires one toilet seat and one urinal per 40 workers for crews of 20 to 199. For 95 workers, you need three toilet seats and three…
Running a fleet in North Texas, I deal with construction sites that cook portable toilets in the sun and generate high-ammonia waste from worker…
Place the standard unit and handwash station on a curbed island where the plow can't reach it. That keeps them clear of snow piles and blade strikes.…
Owen is right about the refusal, but I'll tell you what the driver actually checks for. The driver will dip a sample from the tank before pumping.…
Deb is right about the antifreeze, but she didn't mention that the rental company's driver adds it during the service visit, not at delivery. The…
The route driver will not fish out the phone. The vacuum hose on a vacuum truck is designed to pump liquid waste only, and operators have a strict…
Our company is looking at switching to enzyme-based deodorizers for our construction site units. We run about 200 standard portable toilets on…
OSHA considers this one site because the lots are adjacent and the same crew works all three. The OSHA construction sanitation standard, 29 CFR…
Scatter units along the access roads. OSHA 1926.51 requires at least two units (one toilet and one urinal) for your crew of 40, but on a 60-acre…
We're replacing a water line along a county road, crew of six, and the work face moves roughly a mile every week. Right now we have one standard unit…
I run a 50-person residential construction crew, all men, on a six-month project. We have a tight city lot, and I am trying to save space. I am…
I've been driving a vacuum truck for nine years, and the worst was a January morning after an ice storm. The construction site was a mud pit. I had…
Yes, you add a Saturday pump-out. Two standard units on a Friday service schedule with 35 workers daily are already at the limit by Thursday, and a…
Most rental companies will treat an 80-foot move as a simple relocation, not a full pickup and redelivery, if the unit remains on the same site and…
My GC just ordered a high-rise unit for the 12th floor of our project. I've handled plenty of standard units on the ground, but this is my first time…
We are about to start a six-month garage build on a level gravel driveway with easy truck access. The crew will be four people working full days,…
We have a 20-man framing crew on a six-week residential build. The site is a flat, gravel lot with good truck access. We have two standard units. The…
Nine years driving a vacuum truck, and I've seen it all. Last month, I had to service a standard unit perched on a half-finished bridge deck, 200…
A rental company will not allow you to move their standard portable toilet yourself. Moving the unit yourself voids the rental agreement and any…
Ask for winterization as soon as overnight lows are hitting freezing a few nights a week, not after the first hard freeze. By the time you get a hard…
Our construction crew of 15 needs a portable toilet for eight weeks while we renovate a storefront. There's zero space on the property, so the only…
Marcus is right on the routing, but the driver needs you to confirm the new site has truck access and level ground ready before they roll. A four-man…
Give the rental company a detailed description with the parcel number and the nearest physical address as a starting point. The most important thing…
Give the driver a gate code. A standard unit placed inside the fence is the right call for a dozen workers, which meets the OSHA requirement of one…