Office building renovation: 60 workers over 9 months. How many units?
We're starting a full gut rehab on a three-story office building downtown. The crew will be steady at 60 workers for the full nine months, Monday through Friday, 7 AM to 4 PM. No food service on site, no alcohol, just a standard construction crew. The units will sit on the asphalt parking lot behind the building, with clear access for the vacuum truck every week. I know OSHA 29 CFR 1926.51 requires one toilet per 40 workers, so that's two units minimum. But I'm wondering about the ADA 5 percent cluster rule since we'll have a cluster. Should I order two standard portable toilets and one ADA-compliant unit, or is three standards enough? Also, with nine months of heavy use, is weekly service sufficient, or should I push for twice a week?