Crew jumped from 8 to 22. Do we need a second porta potty?
We started a framing job with eight guys and one standard porta potty on the lot. Subcontractors rolled in this week and we are at about 22 people on site most days. That one unit is getting slammed by midafternoon, and somebody already asked if we are even OSHA compliant anymore.
Does OSHA 1926.51 say we need a second toilet at this headcount, or is one still enough if it gets weekly service? The lunch line is the real problem more than the smell so far.
Open-air site, no building bathrooms we can use. Would a urinal station count toward the toilet number, or do we just need another full standard unit? Looking for what people actually do when a crew grows mid-job without tearing up the weekly contract.